| PROJECT:
GRASSE RIVER
LOCATION:
Up State New York
PROBLEM:
Agency concerns over whether a turbidity curtain system could be
relied on to contain suspended contaminated sediments during a dredging
operation.
SOLUTION:
Elastec/American Marine was called to design, deploy and maintain
two curtains of 700 ft. and 1,100 ft. while maintaining water standards
outside the dredge line. The project lasted over 3 months. AMI personnel
were on site to ensure curtain integrity.
World
Dredging - read the published article
PROJECT:
WALTER F. GEORGE LOCK AND DAM
LOCATION:
Walter F. George Reservoir in Southwest Georgia
PROBLEM:
To contain turbidity within the footprint of a template barge
that was discharging silt into 100' of water. The barge was moved
frequently so the curtain had to adjust from 100' deep to 30' deep.
SOLUTION:
Elastec/American Marine designed and manufactured a first
time ever 100' deep curtain system that floated around and was attached
to the barge. It was equipped with a reefing system to adjust skirt
depth as needed. The curtain worked perfectly maintaining turbidity
levels outside the curtain at below required levels throughout the
duration of the project.
PROJECT:
BLUE RIDGE PROJECT
LOCATION:
Taccoa Reservoir Georgia
PROBLEM:
Control turbidity during the construction of a concrete intake
structure in 70' of water. The work was to be performed from a modular
barge out in the reservoir. Because the depth of the water over
the duration of the project was variable; the curtain skirt needed
to be adjustable.
SOLUTION:
Elastec/American Marine designed a system that where possible
would be attached to the barge elimating the need for curtain flotation.
Specially made steel fittings were fabricated to attach the curtain
to the barges. Special devices were included to keep the curtain
from fouling on the equipment being used to do the work. The curtain
was also equipped with reefing system to allow for adjustments in
curtain depth over the duration of the project. The system worked
perfectly maintaining turbidity levels below that required. The
customer has since purchased more curtain for the expanded second
phase of the operation.
PROJECT:
SAINT LAWRENCE SEAWAY
LOCATION:
Up State New York
PROBLEM:
Contaminated sediments needed to be removed along a large area on
the north bank of the river. A sediment containment system had to
be designed to ensure the contamination was contained in the dredge
area. The river was fast moving with ship traffic and debris creating
a challenge for engineers.
SOLUTION:
Working with consulting engineers Elastec/American Marine designed
a system to ensure the contaminants remain contained while the work
was in progress. The system included a modified turbidity curtain
installed in cells protected by an outer cofferdam perimeter. This
large scale remediation effort took several months to complete.
Our company representative was on hand to ensure the system was
installed properly. The project was a great success with a front
page article appearing in the International Dredging Review, issue
volume 21, number 3, dated April/May 2002.
Read
the Published Article |
PROJECT:
KENSICO RESERVOIR
LOCATION:
White Plain New York
PROBLEM:
Seasonal high turbidity levels were occurring in the areas
where water was flowing into the reservoir. This increased turbidity
in the water, and finding its way into the several water intakes
that service the drinking water needs to New York City and surrounding
area.
SOLUTION:
In the early 1990's a plan was developed which included the
use of our custom made turbidity curtains which would be installed
in the reservoir and deflect the turbid water away from the intakes
and allow the silt to settle out. The curtains are are made such
that they contour the bottom, and in some locations extend out 1,000'
from shore. All in all over 7,000' of deflection barrier is in place
so far. the curtains are performing as expected and have solved
the turbidity problem where they are installed. The work is expected
to continue through 2004.
PROJECT:
NORTHEASTERN ATOMIC POWER PLANT
LOCATION:
Maine
PROBLEM:
A sensitive dredging project in the waterway would require
a staged approach and last two years. Close monitoring of escaping
contaminants required that the job be done in contained cells. The
curtain system had to contain sediments in a large area and be able
to be segmented into smaller cells during the dredging operation.
The curtain had to be in place during winter months and hold up
to snow and icy conditions.
SOLUTION:
Elastec/American Marine designed a unique curtain system
using a large outer curtain with attachment points every five feet.
Specially designed curtain panels could be attached at these points
creating a flexible cell system. This approach allowed the dredging
operation to selectively remove sediments in the desired areas while
not allowing cross contamination.
PROJECT:
RIVER RAISIN
LOCATION:
Monroe, Michigan
PROBLEM:
To deflect the flow of the river while isolating an area where hazardous
materials were being removed from the river bottom.
SOLUTION:
Elastec/American Marine designed and manufactured a 1,800 ft. and
a 1,500 ft. curtain that performed as predicted, ensuring the EPA
water standards were maintained outside the effected area. Commercial
barge traffic continued during dredging.
PROJECT:
TOLT RESERVOIR
LOCATION:
Washington State
PROBLEM:
Seal and protect an area of 60 ft. around an intake tower. Construction
work on the tower was to last 6 months. The curtain had to operate
with as much as 40 ft. fluctuations in the reservoir's water level.
SOLUTION:
Elastec/American Marine took on this challenging project and manufactured
a unique curtain protecting the reservoir while construction on
the tower took place.
Elastec/American
Marine:
1309 West Main, Carmi, IL 62821 USA
Call us at (618) 382-2525 Fax (618) 382-3610 E-mail elastec@elastec.com
Updated May 2004.
© Elastec/AmericanMarine. All rights reserved. |